Suppose that the testing of a system has been outsourced to another organization called “Bug Busters.” This company is located in another country and has marketed themselves as specialists in software testing. You have signed a contract and sent them a copy of all the code, database tables, and files they need to fulfill their end of the contract. The total expected cost or expected budget at completion for this “subproject” is $12,000. The contract stipulates four payments must be made after completion of each of the four testing phases. The time schedule for the testing is as follows: Test Planning 1 week, Unit Testing 2 weeks, Integrated Testing 2 weeks, and Acceptance Testing 2 weeks.
The first phase of testing went as planned, but due to some problems encountered, the second payment that you authorized was more than planned. The project manager in charge of testing has assured you that the few problems they encountered could not be helped and that she does not expect them to continue in the remaining phases. As a smart project manager, you have asked Bug Busters for a work breakdown structure (WBS) and an update of their progress because you are not so sure that these problems are atypical and may continue throughout the testing process. There are still concerns at the end of Phase 3.
Using the following information, conduct an earned value analysis to determine whether you believe the project will remain within its original planned budget of $12,000 and on schedule. Use a spreadsheet software package to determine the Estimate Cost at Completion (ECAC), the Estimate Cost to Completion (ECTC), the Estimate Time at Completion (ETAC), and the Estimate Time to Completion (ETTC) for both typical and atypical variances.
Planned
Value Actual
Cost Percent
Complete Earned
Value
Phase 1: Test Planning (1 week)
Develop Unit Test Plan $ 500 $ 500 100% $ 500
Develop integration test plan $ 600 $ 600 100% $ 600
Develop Acceptance test plan $ 550 $ 550 100% $ 550
Payment 1: $ 1,650 $ 1,650 $ 1,650
Phase 2: Unit Testing (2 weeks)
Code walkthrough with team $ 600 $ 700 100% $ 600
Test software units $ 800 $ 1,200 100% $ 800
Identify programs that do not meet specifications $ 500 $ 500 100% $ 500
Modify code $ 1,200 $ 1,300 100% $ 1,200
Re-test units $ 300 $ 400 100% $ 300
Verify code meets standards $ 200 $ 200 100% $ 200
Payment 2: $ 3,600 $ 4,300 $ 3,600
Phase 3: Integration Testing (2 weeks)
Test integration of all modules $ 600 $ 600 100% $ 600
Identify components that do not meet specifications $ 300 $ 500 75% $ 225
Modify code $ 1,400 $ 1,400 50% $ 700
Re-test integration of modules $ 400 $ 400 75% $ 300
Verify Components meet standards $ 200 $ 200 80% $ 160
Payment 3: $ 2,900 $ 3,100 $ 1,985
Phase 4: Acceptance Testing (2 weeks)
Business Review with Client $ 400 0%
Client tests system $ 800 0%
Identify units and components that do not meet specifications $ 550 0%
Modify code $ 800 0%
Retest units and components $ 700 0%
Verify that system meets standards $ 600 0%
Payment 4: $ 3,850