Create a Gantt chart that shows the WBS. (you may create your diagram in powerpoint or word)
(15 pts) Analyze the fact situation carefully to determine which tasks are concurrent and which ones are dependent on other tasks.
(35 pts) Create a PERT chart that shows the project. Use a format similar to Figure 3-18 on page 82. (you may create your diagram in powerpoint or word)
(10 pts) What is the critical path for this project? How do you know?
If the chart is made in word or PPT, please also send me the word file and PPT file
Please do not directly copy the answers online.
you can refer to the chapter 3 in the book.